How to Build an Underground Brick Dome Water Tank
From Howtopedia - english
Contents |
Short Description
- Problem: to preserve and use water efficiently
- Idea: building an underground brick dome water tank
- Difficulty: Difficult
- Price Range: Rps.6,500 (UK£100)
- Material Needeed: bricks, water handpump, concrete, wooden sticks,iron rod
- Geographic Area: Global
- Competencies:
- How Many people? Up to 5 Persons
- How Long does it take?
The Underground Brick Dome Tank (5m3), Sri Lanka - A Case Study - Technical Brief
Technology challenging poverty
This is RWH system, developed by the CWSSP programme in Sri Lanka. The tank, a 5m3 underground brick built tank, is based loosely on the design of the Chinese below ground biogas tank. Indeed, the Sri Lankan engineer who designed the system had studied for some years in China. This is a good example of cross fertilization of technologies across cultures, as well as the application of appropriate technology.
Again, this system was introduced due to the difficulties faced in bringing water to this community in a conventional manner. There was a lot of opposition to the RWH technology in the area at first, as it was a technology that was not widely known in the area. Now, after 2 years using the rainwater falling on her roof, Mrs. Emsayakar, of Batalahena Village near the town Matara, sees things very differently.
The alternative offered by CWSSP was a handpump per 10 households. This still means walking to collect water. Mrs. Emsayakar joked that they can still use the handpump of their neighbours when they wish. She has not, however, had to do so yet as the harvested water meet all the needs of the family of 5, as long as they conserve water carefully. She also said, however, that she would prefer a piped/pumped supply which would mean that they could use as much water as they wish.
Technical detail
• Find suitable site • Dig pit 0.5m larger than the tank diameter • Plant an iron rod in the centre of the pit, making sure it is vertical. • Construct concrete base. • Start constructing walls using wire from iron rod to maintain the radius. • Once walls are complete backfill the gap between wall and pit with sand. • Make concrete ring beam to the shape shown. No reinforcing is required. Fit overflow pipe at this point if required. • Prepare two wooden sticks - one end an ‘L’ shape and the other a ‘V’ shape. The length of the stick is 2/3 that of the internal diameter of the tank. • Keeping the ‘L’ shaped end of the stick to top of the tank wall, place the ‘V’ end against the iron rod and wrap string or wire around the rod to support the stick. • Start to build the dome shaped roof of the tank with dry bricks. • To start, stick the first brick to the lintel with mortar and support it with the first stick. • For the second brick, stick this to the lintel and the first brick and support it with the second stick. • Push the third brick into place (with mortar) next to the second brick and move the second stick to hold the third brick. • Continue the process as with brick 3 until the first course is almost complete. • The final ‘key’ brick should be shaped to fit tightly allowing for the mortar. • Remove the sticks once the first course is complete. • Continue in this fashion for the subsequent courses. • The dome mouth is constructed in a similar way, but using the bricks length-ways. • Plaster the outside of the dome, then plaster the inside of the dome. • Plaster the inside of the tank. • Plaster the floor o the tank • Cure the tank by wetting for 7 - 10 days. Fill the gradually starting on day 7, filling at a rate of approximately 300mm per day.
|
Item |
Unit |
Unit cost |
Quantity |
Cost (SL Rupees)* |
|
Cement |
bag |
310 |
8.5 |
2635 |
|
Sand |
m3 |
1700 |
0.4 |
680 |
|
3/4 " Metal bar |
m3 |
4000 |
0.1 |
400 |
|
Brick |
Number |
2.1 |
800 |
1680 |
|
Padlo cement (for waterproofing) |
kg |
100 |
0.5 |
50 |
|
Skilled labour |
days |
250 |
4 |
1000 |
|
Unskilled labour |
days |
150 |
12 |
1800 |
|
Total |
8245 |
*(65 SL Rupees = Sterling £1.00 at the time of writing)
The unskilled labour is often provided by the recipient hence reducing the cost of the tank.
References and further reading
This Howtopedia entry was derived from the Practical Action Technical Brief The Underground Brick Dome Tank .
To look at the original document follow this link:
http://www.practicalaction.org/?id=technical_briefs_water
Useful addresses
Practical Action
The Schumacher Centre for Technology & Development, Bourton on Dunsmore, RUGBY, CV23 9QZ, United Kingdom.
Tel.: +44 (0) 1926 634400, Fax: +44 (0) 1926 634401
e-mail:practicalaction@practicalaction.org.uk web:www.practicalaction.org



